Wyuna Road Foreshore Renewal
Oct 8, 2025












The Scope of works:
Demolition and removal of the following structures:
- 12 concrete boat ramps and associated structures
- 2 timber boat ramps and associated structures
- 1 gravel boat ramp
- 1 jetty
- fish cleaning table
- Where necessary, dilapidated revetment comprised of timber, concrete, brick, breeze block or rock
- 1 set of concrete stairs
- All other small ancillary items as identified in the demolition plan
Design, supply and installation of one (1) pelican perch
Construction of:
- 56 m of small-scale rock revetment
- 226 m of rock revetment
- 15 m of small-height, hand-placed rock revetment
- Drainage outfall scour protection
- 2 reinforced concrete slabs for future access stairs to the creek